Audit rack PDU failover capacity, 2N headroom, and the effect of losing either A or B. Model balanced or custom
active/active PSUs, active/passive supplies, ATS-fed single-cord loads, and dual feeds that do not actually transfer.
Planning calculator only. Confirm breaker type, PDU, cord, receptacle, transfer behavior, derating, and local electrical requirements before installation or operation.
Worked A/B failover examples
All examples use single-phase math. “Target utilization” compares demand with the selected continuous capacity; “absolute utilization” compares it with the entered hard rating.
1. Balanced 30 A, 208 V rack that passes
Inputs: 4,200 W, PF 0.95, two 30 A branch circuits, 80% target, balanced active/active, no reserve.
target = 30 A × 0.80 = 24 A; design current = 4,200 W ÷ (208 V × 0.95) = 21.26 A.
Normal: 10.63 A per feed (44.3% of target). Either feed lost: survivor 21.26 A (88.6% of target; 70.9% absolute), leaving 2.74 A or 0.54 kW. Verdict: passes normal and either feed-loss case.
2. Normal state looks safe but failover misses the target
Inputs: 5,200 W, PF 0.95, 30 A at 208 V per feed, 80% target, balanced active/active.
design current = 5,200 ÷ (208 × 0.95) = 26.32 A; normal per feed = 26.32 ÷ 2 = 13.16 A.
Normal: 54.8% of the 24 A target. Either feed lost: 26.32 A, 109.7% of target and 87.7% absolute, with a 2.32 A (0.46 kW) target shortfall. Verdict: passes normal load but fails the selected failover target.
3. Unequal 30 A A-feed and 20 A B-feed
Inputs: 3,000 W, PF 0.95, 208 V, 80% target, balanced active/active. Targets are 24 A on A and 16 A on B.
design current = 3,000 ÷ (208 × 0.95) = 15.18 A; normal is 7.59 A per feed.
A survives: 15.18 A, 63.3% of A target. B survives: 15.18 A, 94.9% of B target, leaving 0.82 A or 0.16 kW. Verdict: passes, limited by B.
4. Active/passive supplies
Inputs: 1,400 W, PF 0.90, 120 V, 20 A per branch, 80% target. A is preferred; B is standby.
design current = 1,400 ÷ (120 × 0.90) = 12.96 A; target = 20 × 0.80 = 16 A.
Normal: A 12.96 A, B 0 A. A lost: B 12.96 A (81.0% of target). B lost: A remains 12.96 A. Headroom is 3.04 A or 0.33 kW. Verdict: passes if transfer behavior is verified.
5. Planning with measured post-failover current
Inputs: normal readings A 9 A and B 8 A, measured surviving-feed peak 19.5 A, 30 A at 208 V, 80% target, PF 0.95 for the kW estimate.
normal total estimate = (9 + 8) × 208 × 0.95 = 3.36 kW. The measured 19.5 A replaces the calculated failure current.
Normal: A 37.5% and B 33.3% of target. Failure: 19.5 A, 81.3% of target and 65% absolute, leaving 4.5 A or 0.89 kW. Verdict: passes the entered limits; confirm the test covered the true workload peak.
Methodology, assumptions, and sources
Reviewed: 17 July 2026. Maintained by the Starlight Tools product and engineering team. Corrections can be reported through the contact page.
Defaults are 208 V, PF 0.95, an 80% continuous target, equal 30 A branch circuits, balanced active/active sharing, and no added reserve. All recommendations use deterministic browser-side arithmetic; inputs are not uploaded.
The calculator does not validate conductor ampacity, code classification, breaker type, phase balance, plug/cord/receptacle limits, individual outlets, temperature derating, harmonics, inrush, ATS transfer time, PSU ride-through, source independence, maintenance procedures, or protection coordination. A pass is a capacity result, not certification or proof of end-to-end redundancy.
Manufacturer references
Frequently asked questions
Why are redundant PDUs often limited to 40% each?
With a balanced A/B load, two feeds at 40% become one surviving feed at 80% after transfer. The 40% value follows from a 50/50 split and an 80% continuous target; it is not a universal electrical limit.
Must A and B originate from independent upstream sources?
Yes, if the goal is end-to-end redundancy. Two rack PDUs connected to the same breaker, UPS, switchboard, or upstream path retain that common failure point.
How do active/active and active/passive power supplies differ?
Active/active supplies share normal load, often approximately 50/50, then the survivor takes the transferable load. Active/passive systems place normal demand on the preferred feed and transfer it to the standby feed after failure.
Should I enter a branch-breaker rating or a PDU nameplate rating?
Choose the matching rating basis. A branch-breaker rating is multiplied by the selected continuous target. An already-derated continuous PDU nameplate rating is not derated again; the calculator then uses the weakest entered breaker, PDU, or internal limit.
What is the difference between kW and kVA here?
kVA describes apparent power and current demand; kW describes real power. For this single-phase model, kW = volts × amps × power factor ÷ 1,000, while kVA = volts × amps ÷ 1,000.
Should I use equipment nameplate load or measured load?
Use approved peak or metered failover data when available. Nameplate values are conservative planning inputs but can overstate typical demand; average measurements can miss startup and workload peaks.
Can A and B feeds have unequal ratings?
Yes, but protected capacity is limited by the weaker surviving path. Enable unequal ratings in Advanced settings and check both A-survives and B-survives scenarios.
Do internal load-bank and receptacle limits matter?
Yes. A PDU input rating does not override a smaller internal bank, outlet, plug, cord, or device inlet limit. Enter an internal aggregate limit when known and review every downstream component separately.
Can an ATS protect single-cord equipment?
An ATS can transfer a single-cord load between independent inputs when its ratings and transfer behavior are suitable. The calculator models capacity, not transfer time, phase synchronization, device ride-through, or ATS reliability.
Why does a passing result not prove end-to-end redundancy?
The result checks deterministic capacity from the values entered. It cannot verify independent utility, generator, UPS, switchgear, cabling, ATS, PDU, outlet, PSU, monitoring, or maintenance paths, nor prove that equipment actually transfers as modeled.