Check the weakest feed
A redundant design is limited by the smaller breaker, cord, receptacle, or PDU rating on either side.
Check a rack PDU or branch breaker against an 80% continuous-load planning target, convert watts to amps, and verify whether A/B redundant feeds can carry the full load after either side fails.
Measured mode treats the entered A and B currents as the normal operating state, then estimates total watts from voltage and power factor.
For dual-corded equipment in A/B mode, the failover check assumes either surviving feed may need to carry 100% of the protected load.
For 100%-rated breakers or other approved designs, change the continuous-load target to match your documented requirement.
Enter load and breaker details to check normal and failover utilization.
| Scenario | A feed amps | A target headroom | B feed amps | B target headroom | Usable target | Status |
|---|---|---|---|---|---|---|
| No calculation yet. | ||||||
This calculator models single-phase PDU feed loading. It is useful for rack PDUs, branch circuits, and dual-corded IT equipment where the total protected load can be estimated in watts or measured in normal amps.
Continuous-load target
target amps = breaker amps x continuous target percent
target watts = voltage x target amps x power factor
Watts to amps
amps = watts / (voltage x power factor)
A/B redundant failover
surviving feed amps = total protected watts / (voltage x power factor)
Recommended breaker rating
minimum breaker amps = worst-case amps / continuous target percent
Schneider Electric explains that standard 80%-rated breakers are applied continuously at 80% of their current rating, while 100%-rated breakers can be applied continuously up to their full rating when installed as required. This page defaults to 80% because that is a common conservative planning target for continuous IT loads.
This tool does not evaluate conductor ampacity, receptacle ratings, PDU internal branch breakers, temperature derating, harmonic current, inrush behavior, three-phase phase balance, or local code details. Treat the results as planning math for conversations with facilities, electrical contractors, and equipment vendors.
In A/B redundant systems, normal operation can look comfortable because the load is split between feeds. The important 2N check is whether either A or B can carry the full protected load during maintenance or failure without exceeding the chosen continuous-load target.
Not usually for a standard 80%-rated breaker. With an 80% target, 30 A becomes 24 A of continuous planning capacity. Only use a higher target when the breaker, PDU, installation, and applicable rules support it.
Breakers and PDUs are limited by current, while IT equipment is often estimated in watts. Power factor converts real power to apparent current for planning. If you have measured amps, measured mode is more direct.
Dual-corded equipment often shares load across A and B during normal operation. If one side fails, the remaining feed may carry the full protected load, so each feed must be sized for that condition.
Use this page for single feed breaker headroom or a single phase-derived feed. For per-phase balance, use the 3-Phase PDU / Phase Load Balance Calculator linked above.
No. The calculator runs in your browser. Copy and CSV export actions use only the values already on the page.
A redundant design is limited by the smaller breaker, cord, receptacle, or PDU rating on either side.
A/B racks can pass normal utilization and still fail the surviving-feed check after one side drops.
Nameplate watts are useful early, but live PDU metering captures real utilization and power factor behavior.
Reserve capacity makes future rack adds and maintenance transfers less likely to create a breaker event.