Utilization rarely hits 100%
Most production fleets spend more time at 30 to 60 percent utilization than at peak.
Estimate server energy use from hardware watts, efficiency, utilization, and redundancy. This calculator converts electrical load into daily and monthly kWh plus a simple cost estimate, so you can size budgets and power circuits.
kWh/day = (servers * watts / efficiency) * utilization * redundancy * (1 + loss) * hours / 1000
Server power planning starts with a simple question: how much electrical power does your IT load really draw from the wall? The nameplate wattage on a server is rarely the full story. Actual draw depends on utilization, the efficiency of the power supplies, and any power-chain losses through PDUs or UPS systems. This estimator takes an average watts-per-server value and scales it using utilization and efficiency so you can model realistic operating conditions instead of peak nameplate ratings.
Redundancy is a major driver in infrastructure planning. N means you provision exactly the servers you need. N+1 adds a single extra unit so the environment can survive a single failure without sacrificing capacity. 2N doubles the capacity for full duplication. In practice, redundancy can also exist at the rack, UPS, or generator layer, but using a multiplier gives a clean first-order approximation for power budgeting.
Efficiency matters because a 90 percent efficient PSU requires more input power than the IT load it delivers. For example, 10 kW of IT load at 90 percent efficiency draws about 11.1 kW at the wall. Add utilization to model average operating conditions, and include a loss factor for upstream distribution (UPS, PDU, transformer). This calculator converts those assumptions into daily and monthly kWh, plus an estimated monthly cost based on your local rate. It is an excellent way to compare consolidation scenarios, density upgrades, and power budget changes without exposing sensitive infrastructure data.
Use the results to sanity-check breaker sizing and rack power limits. If the estimator shows a 12 kW rack, you can compare that to a common 208 V, 30 A circuit budget (about 5 to 6 kW usable after derating) to see whether you need higher-capacity circuits or additional rack distribution. This planning step prevents expensive surprises when hardware arrives and the facility cannot deliver the required amperage.
The model focuses on average load, not peak surge. Some workloads spike during batch windows, backups, or cluster rebalancing. If you expect large variability, consider running multiple scenarios with higher utilization or adding a larger loss factor to reflect cooling, power-factor correction, or transformer inefficiencies. The goal is to keep your power budget conservative enough for operational resilience while still reflecting realistic day-to-day consumption.
Redundancy multiplier: N = 1, N+1 = (servers + 1) / servers, 2N = 2
Effective input watts: W = (servers * watts / (efficiency/100)) * (utilization/100) * redundancy * (1 + loss/100)
Energy per day: kWh/day = W * hours / 1000
Energy per month: kWh/month = kWh/day * 30
Monthly cost: kWh/month * cost per kWh
Suppose you run 50 servers at 350 W average, with 55 percent utilization, 92 percent PSU efficiency, N+1 redundancy, 4 percent PDU/UPS losses, and 24 hours per day. The redundancy multiplier is (50 + 1) / 50 = 1.02.
Effective watts are approximately (50 * 350 / 0.92) * 0.55 * 1.02 * 1.04 ≈ 10,968 W.
Daily energy is 10,968 * 24 / 1000 ≈ 263.2 kWh, and monthly energy is about
7,896 kWh. At $0.12 per kWh, monthly energy cost is roughly $947.50.
It models average power draw using watts, utilization, efficiency, redundancy, and optional loss factors.
Yes. The IT load is divided by efficiency to estimate input power at the wall.
N uses no multiplier, N+1 adds one extra server, and 2N doubles the load for full duplication.
No. Cooling and facility overhead should be modeled separately with a cooling load or PUE calculator.
Yes. All calculations run locally in your browser.
This tool applies efficiency and utilization adjustments to your server load, then converts the result into daily and monthly kWh. Redundancy and loss factors let you plan for resilience and upstream power-chain overhead.
Most production fleets spend more time at 30 to 60 percent utilization than at peak.
Efficiency is highest near mid-load and drops at very low or very high utilization.
N+1 and 2N designs protect uptime but can materially increase energy spend.
Many racks are constrained by circuit limits before they run out of physical space.
Regional electricity prices can double or halve the same hardware operating budget.
Results are estimates based on average inputs and simplified assumptions. Validate power budgets against hardware specifications and facility constraints.